Main Equipment Commissioned/Decommissioned
Technical Data
Power Lines Length/Transformer
Power Demand - Iberic Transmission Grid
Power Demand - National Transmission Grid
Wind Power Generation
Interconnections Flows
Daily Statistics
Net Transmission Capacity
Monthly Statistics
Technical Constraints
Power Plants Scheduled Maintenance Plan
Energy Not Supplied
Average Interruption Time
Regulating Reserve Marginal Price
Weekly Information
Centro De Informação
>
Home EN
>
Technical Statements
>
Main Equipment Commissioned/Decommissioned
Main Equipment Commissioned/Decommissioned
Year in review
1999
Substation
Voltage
[KV]
Equipment
Power
[MVA]
Date
Évora
150/60
Transformador
63
3-12-1999
Trajouce
220/60
Transformador
-170
5-10-1999
Carriche
220/60
Transformador
-126
7-07-1999
Sete Rios
220/60
Transformador
170
8-06-1999
Trajouce.
220/60
Transformador
126
10-07-1999
Pocinho
60/30
Transformador
-20
12-31-1999
Transmission Lines
Lenght
[Km]
Data
Miranda - Picote2 - 220kV
15.5
7-04-1999
Cabo Subterrâneo Carriche - Sete Rios - 220kV
7.6
6-08-1999
Valdigem - Recarei1 - 220kV
-65
6-10-1999
Ramal da Linha Valdigem - Vermoim para Recarei - 220kV
6.5
9-10-1999
Recarei - Vermoim2 - 220kV
-17
9-10-1999
Valdigem - Recarei2 (alteração ao traçado) - 220kV
0.6
9-10-1999
Ramal da Linha Zêzere - Sacavém2 para Porto Alto - 150kV
-16.2
10-01-1999
Porto Alto - Quinta Grande - 150kV
35
10-11-1999
The negative values match to equipment that have been put out-of-service.